Re: ORLIC
Posted: 17 Dec 2017, 14:37
by Barry_Cole
Re: ORLIC
Posted: 17 Dec 2017, 19:52
by Geoff Pearce
Re: ORLIC
Posted: 17 Dec 2017, 19:56
by Geoff Pearce
Just finished dry run fitting of rudder and elevators to check servos , so I can get this bit signed off , then I can finish covering the fuzz with ply.
G
Re: ORLIC
Posted: 20 Dec 2017, 22:45
by Geoff Pearce
MarkDev wrote: ↑20 Dec 2017, 19:28
How do the large model fin/rudder/stabiliser get 'signed off' Geoff?
See you in a week or two for more work.
M
I have an inspector from the LMA. To check the workmanship for the CAA to make sure it's airworthiness
Re: ORLIC
Posted: 22 Dec 2017, 20:48
by Geoff Pearce
MarkDev wrote: ↑22 Dec 2017, 19:46
What I was trying to get at was if all the pieces are inspected separately and are they tested in any way?
M
I think it's up to the examiner,
Re: ORLIC
Posted: 30 Dec 2017, 16:04
by Geoff Pearce
Good news, nearly finished ply covering on fuselage, LMA inspection went well finish fuse and get canopy pulled, then it's the wings
Painting comes later
G
Re: ORLIC
Posted: 04 Jan 2018, 10:21
by matt
Well done Geoff, looks like you will have your joinery indentures soon! Matt
Re: ORLIC
Posted: 13 Jan 2018, 16:27
by Geoff Pearce
First picture shows wiring for elevator servos, and 10mm plastic tubing for push pull rods inside for rudder .
Other three shows panels stuck to fuse. More to do
Re: ORLIC
Posted: 04 Feb 2018, 17:15
by Geoff Pearce
Busy weekend, thanks to Mark helping me to glass fuselage.
Resin, glass then peel ply all went well.
Also starting to finish the plug with resin and a colour additive before rubbing down
Re: ORLIC
Posted: 04 Feb 2018, 17:17
by Barry_Cole
What are you people trying to do to poor Brian, you will give the poor lad a nervous breakdown.
Look away Brian..
BC